![]() |
![]() |
![]() |
|
- Home - Current Status - Phases of Development - Project Timeline - Buildings - Additional Projects - F.A.Q. |
Status Report Archive October 2004 ![]() The first full week of October promises to be the last week of extensive work on phase one of the Colby campus expansion around the Colby Green. By the end of that week the only workers on the site should be landscapers finishing up plantings. Project Manager Steve Campbell said that odds and ends of paving and seeding remained as the month began, but the new crosswalks on Mayflower Hill Drive should be painted and most tasks wrapped up in time for the ceremonial opening of the Colby Green, following the Wesleyan football game on October 9. A walk-through with a punch-list, where College officials, contractors, and architects review the work and enumerate remaining issues, is scheduled following October 9, but Phase I will be finished on schedule. September 2004 ![]() The Colby Green turned green on August 25 and 26, when workers rolled out 90,000 square feet of Maine sod to cover the elliptical lawn. Andrew Drummond '05 recorded the effort as a time-lapse video, and seeing the two days of work condensed is worth the minute that it takes. Though the lawn has been sodded, work continues and the entire area will remain a construction site until mid-September. A granite retaining wall will be built between Mayflower Hill Drive and the edge of the green, handrails need to be installed on granite steps already in place, and areas adjacent to the Colby Green proper still needed to be graded and seeded as September began. The permanent pathway from the new parking lots behind Lunder to the crosswalk in front of Eustis will be completed during the first week of September. Sometime in mid-September the construction zone will shrink to a smaller area around the Schair-Swenson-Watson Alumni Center. At that time the Colby Green will open for general access and its intended uses -- walking, Frisbee games, outdoor classes etc. August 2004 Recent activity includes considerable blasting around the Lunder building since the parking lot between Lunder and Mayflower Hill Drive was decommissioned in July. Some of the new parking lots behind the admissions building have been in use, and a temporary paved walkway connects those lots with the main academic quadrangle. Work scheduled in August includes installation of remaining underground pipes and conduits, storm drains, manholes, and granite steps as well as more earth moving. The second half of the month will see the final shape of Colby Green emerge and paving of permanent roadways and paths. Despite some delays resulting from wet weather the project remains on schedule. Watch the time-lapse movies featuring:To watch these movies, you'll need Apple's Quicktime Player. Download it here. A special thanks goes to Andrew S. Drummond '05 for filming these time-lapse movies. July 2004 ![]() June 2004 ![]() Watch a time-lapse movie featuring of the construction of the Colby Green. To watch these movies, you'll need Apple's Quicktime Player. Download it here. A special thanks goes to Andrew S. Drummond '05 for filming these time-lapse movies. The lawns and paths of the green have taken shape and landscaping is underway along the north access road and parking lot. Paving of the roadways and parking lots will begin by the end of the month. Progress on the foundation and utilities for the alumni center is now clearly visible from Mayflower Hill Drive. During the next month, most of the dirt piles will disappear revealing the true shape of the green.
May 2004 ![]() The Colby Green is gaining momentum. What appeared to be a few piles of dirt and a collection of holes in the former Lunder Lawn this winter is giving way to recognizable areas of the green. The elliptical bowl and the north access road, Colby Green Drive, are taking shape. At the south end, grading has begun for the alumni center parking lot as utility work nears completion. The three ponds and the wetlands that handle site runoff have their final contours and planting is almost done. Four of the largest trees were scheduled to arrive on Friday, May 7. Throughout May the green will continue to take shape:
April 2004 ![]() After a hiatus owing to frost and weather, Colby Green construction resumes the week of April 5, as equipment and material arrive. Construction resumes in earnest during the week of April 12, as excavation for electrical power and communication conduit installation takes place from Cotter Union to Mary Low-Coburn and across toward Foss-Woodman. There will be significant impact on the parking and drive at the north end of Mary Low-Coburn as steam lines, storm drains, electrical conduit, and precast concrete structures are installed. Notices will be sent out about disruptions of vehicle and pedestrian traffic. Earth moving will resume on the green in late April or early May. The Ground breaking is scheduled April 17 for the Alumni Center, the first new building on the green. March 2004 ![]() Construction on the Colby Green was idled during March. With the arrival of spring, earth-moving activity was expected to resume in April. February 2004 ![]() It was one of the coldest Januarys on record, but also one of the driest, allowing work to progress on the Colby Green. Last month fill was placed for portions of the new elliptical lawn, three detention ponds for handling storm water were begun, and water, sewer, and drainage installation continues. The periodic rumble of blasting continued into February. January 2004 ![]() December 2003 ![]() As of mid-December, Colby Green Project Manager Steve Campbell reported that about 5 percent of the project's approximately 60,000 cubic yards of soil has been put in place. Blasting will continue through January, mostly to make trenches for utilities, including sewer lines. Dynamite also will be used to excavate pits in the bedrock so future trees will have sufficient soilfor their roots. The utilities earthwork is expected to continue through February, when workers anticipate a pause during the hardest of the winter freeze-up. Current Status | Phases of Development | Project Timeline Colby Home | Search | Directory © Colby College Office of Communications
|
||