Modeling Energy Usage in Waterville
Peter
Smithy ‘12
Noah Teachey ‘13
Environmental
Studies Program
Colby
College
Waterville,
ME
Abstract
The
goal of this research was to calculate the energy load of buildings in
Waterville and to determine the feasibility of building a 5 Megawatt power
plant at one of two sites. This would
meet the heating requirements of the city through the piping of excess heat to
the buildings. We determined the heating
load by multiplying square footage with an estimate of energy load per square
foot per year and the paths of the pipes were based on preexisting sewer
pipes. Our preliminary analysis found
that hypothetical power plant site 1 is more efficient in terms of piping
distance to 433 commercial and residential zones than site 2.
Introduction
The use
of large power plants in the distribution of power across great distances is
inefficient due to the loss of energy as low quality heat in the conversion of
heat to electricity. It has been demonstrated that in 40-55 MW power
plants the second law efficiency varies from 18% - 23% (Kumar 2009). In
other words, potentially useful energy escapes in the form of waste heat,
resulting in a relatively resource-intensive energy extraction process.
Rather
than releasing excess heat as heat pollution, as is the practice of many large
power plants, greater energy efficiency would result if it were possible to
capture and utilize the excess heat energy. Demand for such heat energy
as a means of heating buildings incentivizes the construction of pipe networks
from power plants to communities for which there is a demand for the heat.
This scenario loses feasibility the further a power plant is from the
community that might benefit from the heated water vapor. The purpose of
this research is to calculate the energy load in Waterville, ME in order to
determine the viability of heating the community with waste energy from a
proposed 5 MW power facility.
Methods
After obtaining vector data
including the square footage of buildings and the location of sewer pipes, we
used GIS software to apply a figure for the yearly energy load (0.5 gal. of oil
/ sq. ft. yearly) to the square footage of buildings to estimate total yearly
energy load. In order to display the more energy-intensive areas of
Waterville, we ran a Kernel density analysis in which the variable displayed
was total energy load. We selected two hypothetical power plant locations
for comparison; one at the site of a railroad hub and another at the site of a
former paper mill. We used a zoning vector layer to sum the total energy
load of buildings within each zone and calculated a centroid
for each zone before measuring distances along sewer pipes from each
hypothetical power plant location to the centroid of
each residential and commercial zone.
Results
In
carrying out the analysis of distance along water mains from the two
hypothetical power plants to the centroids of zones
designated residential or commercial, we found that Plant Location 1 served 433
centroids by tracing 1,267.085 km of piping whereas
Plant Location 2 accomplished the same task by tracing 1,355.560 km of piping.
However, Plant Location 2 used less piping than Plant Location 1 in
serving the 36 zones designated Commercial A (primarily of downtown
Waterville), with only 81.107 km of piping as opposed to Plant Location 1’s
92.813 km, as summarized below.
Table 1. Total pipeline
lengths needed to serve the centroid of each zone for
a given zoning classification. A new line is generated from the power plant to
each zone. The number of zones served is equal for both plant locations and
indicated.
|
Zoning Class |
||||
|
Scenario |
Downtown/
Commercial A (36 zones) |
Commercial B,C,D (81 zones) |
Residential A,B,C,D (316 zones) |
TOTALS (433 zones) |
|
Location 1 |
92,813 |
229,565 |
944,707 |
1,267,085 |
|
Location 2 |
81,107 |
300,883 |
973,570 |
1,355,560 |

Figure 1. Zoning map of
Waterville coded by increasing energy load from light to dark red. The color
range indicates a range of 50-350,000 gallons of oil used per year for heating.
Brighter areas are localized hotspots of energy load, computed from individual
building load.

Figure 2. A three-dimensional
representation of energy load within Waterville, with rivers included, where
higher elevations correspond to greater energy load.

Figure 3. A
map of downtown Waterville, where buildings with higher energy loads are
indicated by darker reds and hotspots of heating load are illuminated.
Discussion
This
finding demonstrates that the first hypothetical power plant location, near the
railroad hub, is a more efficient location in terms of piping distance to all
433 residential and commercial zone centroids.
Piping distance relates to the quality of heat that can be extracted from
the waste heat of second law-inefficient operations in a 5 MW power plant
because heat is lost with every additional meter of piping through which it
must travel to reach its destination. However, if a greater degree of
selectivity is used in building the infrastructure through which the excess
heat is distributed and a lesser number of zones is
served, then Plant Location 2 has the potential to be more efficient. If,
for example, a power plant project only produces enough heat energy for use in
buildings in downtown Waterville then the second location is more efficient
than the first. There are a number of other variables that this research
does not consider, such as the fixed costs of building the facility and
complying with codes that might alter the optimal placement of the facility.
Additionally, the differentiated sizes of piping will play a part in
further analyses of the data as trunk piping must be optimally placed to best
serve the needs of the community with branch and connection piping feeding off
of it.
Conclusion
•
Hypothetical
Plant Location 1 is the most efficient location in serving all 433 residential
and commercial zones in the Waterville area along pre-existing water main
pathways when compared with hypothetical Plant Location 2.
•
Hypothetical
Plant Location 2 has the potential to be more efficient in serving the
Waterville area depending on which and how many zones are served.
•
Consideration
of differentiated pipes may change the results and will allow for a rough
estimation of total costs of construction of the pipe network.
•
This
analysis represents a preliminary effort to display heating load and suggest
the most efficient of two hypothetical power plant
locations. Actual pipeline locations
will most likely diverge from preexisting water mains should this study be
advanced further.
Acknowledgements
We
would like to express gratitude to Prof. John Joseph of the Mid Maine Sustainability
Coalition for suggesting the need to explore this topic and for providing
several figures, Paul Castonguay with the City of
Waterville Assessor’s Office for Waterville building, road, and zoning data,
and Jefferson Longfellow, P.E. with the Kennebec Water District for water main
data. Additionally, special thanks go to Professors Philip Nyhus and Manny Gimond for
technical assistance.